In February 2020, Henan FLAG Crane Company was selected by the EPC to provide an overhead crane for the Azito's phase IV power Plant, located in the Yopougon district of Abidjan in Cóte d'lvoire.
In March 2024, AZITO ENERGIE had the plan to remove the rotor of the Gas Turbine (GT) for repair works the first time since in operation. Due to the highly sensitive requirements of this activity. AZITO ENERGIE requested FLAG Crane to send an engineer to fully restore the functionalities of the crane. and to assist till the rotor is removed from the GT casing.
On May 13th, 2024, AZITO ENERGIE tested the FLAG Crane's 95t overhead Crane in all aspects along, with Azito's subcontractor GE's team responsible for the removal of the rotor. and the crane worked fully in accordance with the requirements and at the satisfaction of all parties.
On May 14, 2024, AZITO ENERGIE successfully removed the Gas Turbine rotor. which enables us to be on the right track, to contribute to the security and the stability of the country's power sector.
Previous: What’s different types of bridge cranes?